2017 Streets Project Update
Week of September 25th: Contractor plans to complete all earthwork, drainage work, and base repairs on St. Anthony Street, St. Lawrence Street, and Ikeler Street east of Matlack Avenue
Week of October 2nd: Contractor plans to undertake the paving on St. Anthony Street, St. Lawrence Street, and Ikeler Street east of Matlack Avenue
October 2nd through October 4th: Contractor will be placing new layers of stone on the gravel parking lots behind LaCasa Pizza and the Towne Tavern. These gravel parking lots will be closed all three days.
Week of October 23rd: Contractor plans to mill and pave Ikeler Street from Matlack Avenue to Maclay Avenue